Cost Estimating: Rough Order Magnitude Estimate: 19 to 54 gpm Forced Draft Decarbonator

Cost Estimating: Rough Order Magnitude Estimate: 19 to 54 gpm Forced Draft Decarbonator

Link to main page: (link)

Cost Estimating: Rough Order Magnitude: Forced Draft Decarbonator
Remove CO2 from water.

** Costs below are based on Contractor providing entire project **

Costs based on project located in the USA.

Rough Order Mag Estimate – Aug 15, 2026

ROM (US Dollars) (Includes Contractor’s Markups)
 19 GPM26 GPM34 GPM44 GPM54 GPM
 5′ Deep PPL Packing5′ Deep PPL Packing5′ Deep PPL Packing5′ Deep PPL Packing5′ Deep PPL Packing
      
Vertical Vessel [20 psi max.]24,36026,18529,81533,94536,815
Water Storage: 2 minutes water storageinclinclinclinclincl
Fan (for air inlet)inclinclinclinclincl
Duct (for air inlet) [20 psi max.]inclinclinclinclincl
Random Packing: PPLinclinclinclinclincl
Spray Nozzleinclinclinclinclincl
Mist Eliminatorinclinclinclinclincl
Bed Limiter & Packing Supportinclinclinclinclincl
Sub Total 24,36026,18529,18533,94536,815
      
 The following are adders:    
Gauge Glass1,1251,1251,1251,1251,125
Level Switches:  NEMA 4X  (Two)1,2001,2001,2001,2001,200
Rain Cap – PVC  (for vent)7808658651,0751,170
Butterfly Damper – PVC (for air inlet)535625625655690
 Use Use 28,000 Use 30,000 Use 33,000 Use 38,000 Use 41,000
Install at Project Site (Includes Anchor Bolts & Guy Wire).  Includes an Allowance for inbound freight and freight to jobsite.30,00030,00030,00030,00030,000
 Sub Total 58,000 60,000 63,000 68,000 71,000
      
Vessel and Duct [at 50 PSI] in lieu of [at 20 PSI]ExtraExtraExtraExtraExtra
      
Note: Manufacturers, Model Numbers, and materials of construction to be selected by Decarbonator manufacturer or Contractor.
      
Test Kit / Analyzer [pH / CO2]ExcludedExcludedExcludedExcludedExcluded
Pumps (and related valves)ExcludedExcludedExcludedExcludedExcluded
Water Inlet, Water Outlet & Manual Isolation ValvesExcludedExcludedExcludedExcludedExcluded
Y-StrainerExcludedExcludedExcludedExcludedExcluded
PRV(s)ExcludedExcludedExcludedExcludedExcluded
TransmittersExcludedExcludedExcludedExcludedExcluded
SilencerExcludedExcludedExcludedExcludedExcluded
External PipingExcludedExcludedExcludedExcludedExcluded
Check Valve(s)ExcludedExcludedExcludedExcludedExcluded
Anode(s)ExcludedExcludedExcludedExcludedExcluded
Chemical Feed System / ChemicalsExcludedExcludedExcludedExcludedExcluded
Alarm / LightsExcludedExcludedExcludedExcludedExcluded
Panel(s)ExcludedExcludedExcludedExcludedExcluded
Electrical (conduit, fittings, wiring)ExcludedExcludedExcludedExcludedExcluded
Concrete / Steel Supports (to support decarbonator)ExcludedExcludedExcludedExcludedExcluded
Ladder / Cage / Platform/ RailingExcludedExcludedExcludedExcludedExcluded
Demolition / Removal of Existing / SiteworkExcludedExcludedExcludedExcludedExcluded
Treatment of Off-gasExcludedExcludedExcludedExcludedExcluded

Vessel and piping of: Lined Ductile Iron, Rubber Lined Carbon Steel or Stainless Steel would be extra.

Rough Order Magnitude (ROM) Estimate Aug 15, 2026